Brick, Stone and Boards

September 3, 2014

Home Construction

It’s been a little while since our last update because progress before the holiday seemed a little to drag….but…

The masons returned to work this week and have been making good progress on both the north ‘tower’ stone and the rear of the house brick.

The carpenters have been getting deep into the detail work building soffits, tweaking framework while also installing the last of the windows.

The electricians have been installing lights cans, gem boxes and bending pipe into place.

The plumber let the sump hose dangle and during Monday’s rainstorm – resulted in water ejecting into the basement.

The fire-suppression guys finished installing most of the orange pipe…and sprinkler heads.

The low-voltage guys have been installing wires for speakers, network connections, stereo components and cable.

Anne and I have been quite busy as well – working on: fireplaces, wine cellar racks, light fixtures, plumbing fixtures, window coverings, flooring, tile and marble.

IMG_1725

Looking out of the great room

IMG_1724

The back of the house

IMG_1708

Final windows installed in the loggia

IMG_1720

Good progress on stoning the North ‘tower’

IMG_1729

The A/V closet – under the basement stairs

IMG_1735

Beam, pipes and cables … site of future soffit

IMG_1737

Roof flashing and Mrs. Kruckman’s house (Looking south out of BR4)

IMG_1741

Patio door and bricks staged by loggia / MBR

IMG_1743

Bricking in the garages

IMG_1745

Garage bricks and mudroom window (awaiting sill)

IMG_1747

Frontal view

IMG_1748

Limestone sills – heavy!