September 3, 2014

0 Comments

Brick, Stone and Boards

It’s been a little while since our last update because progress before the holiday seemed a little to drag….but… The masons returned to work this week and have been making good progress on both the north ‘tower’ stone and the rear of the house brick. The carpenters have been getting deep into the detail work […]

Continue reading...

August 25, 2014

0 Comments

Exterior Shots

It’s been a little while since we updated the front views…so here they are. There’s also a few pics of the basement progress and Hannah’s pocket doors…we noticed these while she and I were taking measurements of her room for furniture arrangement.  We settled on swivel/rocking chairs…super comfy!  

Continue reading...

August 19, 2014

1 Comment

Visible Progress

    We are happy to see some visible progress again…now that the fascia is all installed. The electricians, plumbers, roofers and HVAC guys continue installing their respective systems.  Sara (cabinets) is finalizing her plan and the low-voltage guy (Chuck) will be coming by on Thursday to plan for TV/AV/Phone etc. The masons returned to […]

Continue reading...

August 18, 2014

1 Comment

Photos from UK Move in

Since the girls will be in two different states on the first day of school, we took the annual picture on the bench early. The volunteers at UK were awesome! We pulled up and they unloaded the car for us. Here they are unloading the rooftop carrier. Great investment! Next they loaded everything from the […]

Continue reading...

August 14, 2014

0 Comments

One Last Look…Before Dorm Life Hits

Here’s Madeline – taking a final walk-through (lie down?) between the pine framing that will by her Thanksgiving return to Libertyville in November be hung with wallboard and resemble truly what her bedroom suite will look like. Elsewhere in the house – the carpenters, roofers, electricians, plumbers and HVAC installers toil away.  

Continue reading...

August 13, 2014

0 Comments

Raising the Roof

Here’s something new…a roof.  Brad Hall (Rick’s son) has his crew of five up on the roof…after one day’s work they’re about 1/3 done. On the inside, Ted built the shed in the attic for the furnace and has been finishing up framing.  Dan and Al (electricians) are moving along as are the plumbers and […]

Continue reading...

August 7, 2014

0 Comments

Time is Dragging

Well…we noticed last night that we REALLY need to look closely to notice the day’s progress of our craftsmen.  Working in the “details” must be equally exhausting for them, too. – Ted & The Carpentry Crew continue working on the fascia.  No doubt, the details and curves of the roof make this a complicated effort.  Ted said that […]

Continue reading...

August 4, 2014

0 Comments

Fascia, Stone and Electricity

Well, hopefully we have have switches, outlets and light fixtures just where everyone would expect to find them – if not, Anne and I wasted FIVE hours of our lives looking at just those things.  We met Rick and Dan (electrician) today at the house after going through the drawings last night. While at the […]

Continue reading...

July 30, 2014

0 Comments

Busy Times Continue

Here are some photos that show progress that the various trades are making…as Anne said in her last post, it’s a real beehive of activity over there lately. We met today with: cabinet wiz (Sarah), stair master (Ken), master carpenter (Ted), finishing carpenter (Joel) and had lunch with Rick.  We also had several visitors today: […]

Continue reading...

July 28, 2014

0 Comments

So much going on…

Jeff and I met with Rick today to discuss our fireplace options. As soon as I pulled up to the house I couldn’t believe how many guys were there working. The plumbers, masons, roofers and carpenters were all hard at work. Below are a few pictures capturing their hard work.           […]

Continue reading...